Paris Orly: runway 4 closed until 17 December 2026, flights reorganised

Published · Updated · VolClaim

Resurfacing works on runway 4 at Paris Orly continue until 17 December 2026. While it is closed, all traffic uses the airport's two other runways, and the reduced capacity has led airlines to cut frequencies, move departure times or transfer flights to Paris Charles de Gaulle.

More than four months of works

Runway 4, also known as 06/24 and 3,650 metres long, has been closed since 10 August 2026 for a full rebuild: new pavement, upgraded runway lighting and a reconfigured taxiway layout. According to Air Journal, commercial reopening is planned for 17 December 2026 at the latest.

In an information letter to local residents, the management of Paris Orly airport (Groupe ADP) explains that all take-offs and landings have moved to runways 2 and 3. Each can handle up to 30 movements per hour, fewer than usual, and the night curfew from 23:30 to 06:00 remains in force throughout the works.

Around 3,000 flights affected

Before the works began, the French aviation industry federation FNAM estimated that around 3,000 flights could be cancelled, rescheduled or moved to Paris Charles de Gaulle over the whole period, many of them during the summer peak.

Transavia, a major carrier at Orly, announced frequency cuts, slot changes and the transfer of some operations to Charles de Gaulle, according to L'Écho touristique.

What it means for your trip

If you are flying from or to Orly before mid-December, including during the French autumn half-term, check the times and the airport shown on your booking regularly: a flight may have been rescheduled or moved to Paris Charles de Gaulle, which also affects any pre-booked parking or public transport journey.

Because the closure was planned months in advance, a cancellation or schedule change notified more than 14 days before departure gives a right to a refund or another flight, but not to fixed compensation. However, a cancellation announced less than 14 days before departure or an arrival delay of 3 hours or more may give a right to compensation, depending on the reason given by the airline.

If you are kept waiting at the airport, the airline must provide meals and refreshments, and a hotel if an overnight stay becomes necessary.

Frequently asked questions

How long will Orly's runway 4 be closed?

Commercial reopening is planned for 17 December 2026 at the latest, according to information published by Groupe ADP, the French ministry for ecological transition and the trade press.

Are night flights allowed at Orly during the works?

No. According to Groupe ADP, the curfew from 23:30 to 06:00 remains in place for the whole duration of the works.

Sources

  1. Fermeture de la piste 4 à Paris-Orly pendant quatre mois : 3 000 vols impactés à partir d'août — Air Journal (17 mai 2026)
  2. Aéroport d'Orly : quatre mois de travaux complexes et 3 000 vols impactés dès le mois d'août — L'Écho touristique (19 mai 2026)
  3. Travaux de la piste 4 : courrier d'information de l'aéroport Paris-Orly aux riverains — Groupe ADP, aéroport Paris-Orly (juin 2026)
  4. Aéroport Paris-Orly : fermeture de la piste 4 du 10 août au 17 décembre 2026 — Ministère de la Transition écologique

News written by the VolClaim editorial team, a service operated by TETRIS GROUP LLC, based on the sources cited. Information may change: always check your flight status with the airline.

Read in: Français · Deutsch · Español

More air travel news

← All air travel news